Can I add a floor or extend my building in Lebanon, and what permit do I need?
On this page
Short answer
Yes, within your plot's planning limits[1]. An extra floor or extension is building work, so it needs a prior building permit from the head of the municipality, or the governor or caimacam outside municipal areas[2], with plans signed by a responsible engineer and registered with the Order of Engineers. An existing small building within the Law 294/2022 limits can use the cheaper model-design permit instead, with a structural engineer's report[3].
Also asked as: “Can I add a floor to my building in Lebanon and what permit is needed?” · “Permit to build an extra floor in Lebanon” · “Can I build on my roof in Lebanon?” · “Extending a house in Lebanon: which permit?”
A floor added without a permit after 1 January 2019 is outside the Law 139/2019 settlement scheme[4]. Under the Building Law it can still be permitted, with a fine of twice the fees, only if it conforms to the rules; otherwise it must be demolished[2]. This page covers what was published up to 17 October 2026.
Key facts
- The law
- Law 646 of 2004 (Building Law), Art. 1[2]
- Who issues the permit
- the head of the municipality, or the governor or caimacam outside municipal areas[2]
- Who signs the plans
- A responsible engineer; the plans are registered with the Order of Engineers in Beirut or Tripoli[2]
- Decision deadline
- 2 months on an executed road, 6 months otherwise[2]
- Permit valid for
- six years, renewable once for two years[2]
- Small-building route
- Law 294/2022, up to 2 floors, 250 m² total, 150 m² per floor, 7.5 m high[3]
- Floor built without a permit
- Permit only if the work conforms, with a fine of twice all the fees due[2]
Which permit an extra floor needs
Law 646 of 2004, the Building Law, requires a prior permit to build, convert, renovate or renew any building[2]. A responsible engineer signs the application and plans, and they are registered with the Order of Engineers in Beirut or Tripoli. The permit is issued by the head of the municipality, or the governor or caimacam outside municipal areas.
Maintenance, retaining walls, plastering and renovation of lawful or regularised buildings need only an engineer's declaration, valid one year[2]. That route is for renovating a flat. Structural changes and additions, extra floors included, go through the full permit.
For small buildings there is a second route under Law 294/2022. It lets the owner of a plot with an existing building use the model-design regime within that law's area and floor limits, with a structural engineer's report[3]. The two routes compare like this:
| Point | Full building permit | Model-design permit |
|---|---|---|
| How big | Set by the zone's planning rules[1] | Up to 2 floors, 250 m² total, 150 m² per floor, 7.5 m high[3] |
| Structural check | A soil-bearing study with the application[2] | a structural engineer's report[3] |
| Fees | Amounts not published; the authority gives you its approved land value estimate[2] | 50% off permit and municipal fees[3] |
| Valid for | six years, renewable once for two years[2] | two years, renewable once for two years[3] |
| Other limits | The zone's rules[1] | Usable once per owner[3]; no basements |
| Where and until when | Wherever the zone's planning rules allow building[1] | Not in governorate centres, main cities, archaeological and tourist areas, reserves, landslide or flood zones[3]; in force for five years from 21 April 2022 |
More in the model-design fee discount.
How much you can add depends on the plot
The floor area a plot can carry is set by its exploitation factors. According to a 2023 academic paper, the decrees implementing the Building Law define a surface exploitation factor and a total exploitation factor for each plot, and balconies may add up to 20%[1]. The factors are fixed zone by zone in each area's planning rules. We found no published figures for any zone, and no source on height or floor limits per zone.
Ask the municipality and your engineer for your zone's surface and total factors, maximum height and number of floors, and how much of that the existing building already uses. If the existing floors already use the full allowance, there is nothing left to add. See what the exploitation factor is.
A permit is granted under the laws and zoning rules in force on the day it is granted. If errors are found later, only the part already built counts as an acquired right[7]. A 2018 BAU Journal article names three bodies involved in a permit: the Order of Engineers, the General Directorate of Urban Planning and the municipality[8].
Check the existing building first
Al Jazeera reported in February 2026 that local officials, after the Tripoli collapse of 8 February 2026, said the 2023 earthquake had damaged older buildings, many of them weakened by irregular added floors[9]. The owner must keep the building maintained, stable and sound, and must commission engineers to inspect it when needed or when the municipality asks[2]. On the model-design route the structural report is a legal condition[3]. On the full route, ask your engineer for a written assessment of the existing frame anyway, before anyone designs the new floor.
Structural strengthening and roof replacement are allowed only in lawful or regularised buildings[2]. None of our sources says how to prove that an existing building is lawful before you extend it. Ask your engineer to compare the building with its permit and occupancy plans, and ask the municipality whether it holds any violation report.
A violation is written on the property's real folio only at the request of the municipality or the technical administration, so a clean Land Registry extract does not prove there is none[2]. The municipality gives no clearance until fines are paid and the violation is settled. Older violations, built from 13 September 1971 to 31 December 2018, fall under Law 139/2019[4,10]. See legalising a building without a permit.
Shared buildings and selling the new floor
The top roof is a common part of the building, unless the building's own management regulation at the Land Registry allocates it differently[5,6]. Under the co-ownership decree, the owners' association may add a building by at least 75% of the owners' votes, although acts of disposal otherwise need unanimity. According to the Lebanese Army magazine's summary of the decree, changing units' shares in the common parts needs every owner's vote[5]. Our sources do not say which of these rules a new floor triggers, so ask a property lawyer before you commit. More in what the co-ownership law says.
The bar is high even for small jobs. In a subdivided building, a declaration for external maintenance or cosmetic works needs approval of the owners' association or 75% of the owners[7,11].
To sell the new floor as its own flat, it needs its own folio. The Land Registry will not subdivide a building into units without an occupancy permit plus electricity and water connection certificates[2]. A building's parts can be registered as separate units only if the construction complies with the building laws[11]. A provisional occupancy permit allows connections and living there, but not final subdivision, sale or registration[7].
How to add a floor, step by step
- Get an official Land Registry extract for the plot. Request it at the land registry office for the property's area[12,13] and give the office the governorate, district, real estate zone, property number, section and block[13,14] (the last two where they apply). It shows the owners, their shares, mortgages, seizures and pending court actions[13,15]. Copies from the website or OMT are unofficial; an official certificate from the land registry is needed for any transaction or court use[13,14,15,16]. Legalmondo put the fee at USD 5 in June 2025[13]. It also says anyone may request a certificate, so someone in Lebanon can collect it if you are abroad, but that none is issued while a lien or registration on the plot is in process. More in how to get a Land Registry extract.
- Hire a responsible engineer. They sign the application and plans, which are registered with the Order of Engineers in Beirut or Tripoli[2]. Ask them in writing for your zone's exploitation factors and height limit, how much area the building already uses, whether it matches its permit plans, and which route fits.
- File the application. Your engineer prepares the file. The permit is issued by the head of the municipality, or the governor or caimacam outside municipal areas[2]. Within one month of registering the application, the authority must give you a certified copy of its approved land value estimate. All fees are paid before the permit is issued. We found no published fee amounts, so ask your engineer for a written estimate before you file.
- Wait for the decision. The deadline is 2 months on an executed road, 6 months otherwise[2]. If the administration stays silent, you may, within six months after the deadline lapses, apply to the competent authority directly or through a notary, declaring yourself implicitly licensed and attaching the fees due. Our sources do not cover the later risks of that route, so ask a lawyer first.
- Build under the permit. No slab or roof may be poured without a pouring permit signed by the responsible engineer[2].
- Apply for the occupancy permit. Once the work, facades included, is complete, the owner applies with as-built plans registered with the Order of Engineers[2]. The administration must decide within one month.
It depends on
- Your zone. The exploitation factors and height limits are set zone by zone[1]. Ask the municipality and your engineer for your plot's figures.
- Whether the existing building is lawful. For older violations, Law 139/2019's text gives two years to file but quadruples fees after one year, and the articles are marked as amended by Law 10/2022, whose text we did not read[4,10]. No source says whether a window is open now; ask the municipality or a lawyer.
- Where the plot is. The model-design route is closed in governorate centres, main cities, archaeological and tourist areas, reserves and landslide or flood zones[3]. Ask the municipality whether your plot qualifies.
- Whether you plan to sell the floor. Selling it as a separate flat needs an occupancy permit before the Land Registry will subdivide[2].
Common questions
Can I add a floor now and legalise it later?
Work started without a permit is stopped and a violation report is drawn up; if it conforms to the rules, the permit comes with a fine of twice all the fees due[2], and if not, it must be demolished. The Building Law also fines those responsible LBP 2,000,000 to 100,000,000, or LBP 4,000,000 to 200,000,000 and/or one week to 15 days in jail for carrying on after a stop order; these are nominal 2004 amounts and we found no revaluation. Violations after 1 January 2019 are not covered by the Law 139/2019 settlement[4].
How much does a permit to add a floor cost?
Can I sell the new floor as a separate apartment?
Only after it is subdivided at the Land Registry, which needs an occupancy permit plus electricity and water connection certificates[2]. Until then it has no folio of its own.
Is the model-design law still in force?
Law 294/2022 runs for five years from 21 April 2022[3]. We found no confirmation that it has been extended, so ask the municipality before you plan around it.
Sources
Checked against these sources. The numbers in the text point here.
- 1.Lebanese building law between texts, application gaps and land scarcity
Journal of Planner and Development (JPD), Center of Urban and Regional Planning for Postgraduate Studies, University of Baghdad · 1 Feb 2023 · read 17 Oct 2026
- 2.Law 646 of 16/12/2004 (Building Law), amending Legislative Decree 148 of 16/09/1983
Lebanese Republic, Ministry of Public Works and Transport, Directorate General of Urban Planning (DGU) · 16 Dec 2004 · read 17 Oct 2026
- 3.Law 294 of 14/4/2022: temporary reduction of fees for some building permits built to model designs
Lebanese University Legal Informatics Center (DGU copy of Law 294/2022) · 14 Apr 2022 · read 17 Oct 2026
- 4.Law 139/2019 on settling building violations committed between 13/9/1971 and 31/12/2018 inclusive (Arts 3, 5, 7, 9 marked as amended by Law 10/2022)
Lebanese University Legal Information Center (legiliban) · 9 Jul 2019 · read 17 Oct 2026
- 5.Managing the ownership of floors and flats (Dr Nader Abdel Aziz Chaffi, Army Magazine issue 302-303, August 2010)
Lebanese Army (Army Magazine, "We and the Law" section) · August 2010 · read 17 Oct 2026
- 6.Legislative Decree No. 88 of 16/9/1983 on co-ownership of built property
Joseph Wanis Official Site (lawyer Joseph Wanis) · 22 Mar 2019 · read 17 Oct 2026
- 7.Decree 15874 of 5/12/2005 implementing the Building Law, as amended by Decree 617 of 8/8/2007
General Directorate of Urban Planning (DGU), Ministry of Public Works and Transport · 5 Dec 2005 · read 17 Oct 2026
- 8.Building Permit: A Critical Review of the Legal Framework in Lebanon (abstract)
BAU Journal - Health and Wellbeing (Beirut Arab University, Digital Commons) · undated · read 17 Oct 2026
- 9.Deadly tower collapse has locals in Lebanon's Tripoli asking: Are we next?
Al Jazeera · 20 Feb 2026 · read 17 Oct 2026
- 10.Law 139 of 9/7/2019 settling building violations committed 13/9/1971 to 31/12/2018
Lebanese University Legal Informatics Centre (copy of DGU text) · 9 Jul 2019 · read 17 Oct 2026
- 11.Condominium Ownership of Built Immovables in Lebanese Law — Eighth and Final Part of the Practical Guide to the Lebanese Code of Real Property
Kallas Law Firm · 25 May 2026 · read 17 Oct 2026
- 12.Inheritance in Lebanon: Probate, Estate Declaration and Inheritance Tax (2026)
Kallas Law Firm · 27 Jun 2022 · read 17 Oct 2026
- 13.How to Find Real Estate and Land Register Information in Lebanon
Legalmondo · 17 Jun 2025 · read 17 Oct 2026
- 14.OMT: Viewing Title Registers (Land Registry service page)
OMT (Online Money Transfer S.A.L.) · undated · read 17 Oct 2026
- 15.Lebanon Asset Search: How to Find Real Estate and Company Ownership Records
Kallas Law Firm · 25 Oct 2025 · read 17 Oct 2026
- 16.Viewing Title Registers Electively Through OMT
OMT (Online Money Transfer S.A.L.) · 13 Oct 2020 · read 17 Oct 2026
Related questions
- What are the steps to get a building permit from the municipality in Lebanon?You need a prior permit, signed by a responsible engineer and issued by the municipality. The steps, deadlines, documents and what is not published.
- What is the exploitation factor and how much can I build on my plot in Lebanon?It depends on the zone. What the surface and total exploitation factors are, how to get your plot's figures, and the model-design route for small houses.
- How do I find the zoning and building ratios for a plot in Lebanon?No office is published for it: get the plot's extract, then have an engineer check the master plan and exploitation factors. Steps and what to ask.
- Can a building built without a permit be legalised in Lebanon?Often yes, if it conforms, for a multiple of the permit fees. Whether Law 139 still takes files in 2026 is unconfirmed. Costs, sale effects, steps.
- Is there a building permit fee discount for small model-design houses in Lebanon?Yes: Law 294/2022 halves permit and municipal fees for houses built to official model designs, up to 2 floors and 250 m². Who qualifies and the deadline.
- How can I find out if a property has building violations or unpaid fines before I buy it?Get an official Land Registry extract, ask the municipality for its clearance, and have an engineer check the permit. What each shows and what it misses.
- What does Lebanon's co-ownership law say about common parts, shares and votes?Decree 88/1983 makes roofs, lifts and stairs common parts and counts shares and votes out of 1,000. Majorities, association rules and checks.
- How do I know whether a building in Lebanon is at risk of collapse?We found no public danger list: check the papers, ask the municipality and hire a structural engineer. Owners' legal duties and what Tripoli showed.