What are the steps to get a building permit from the municipality in Lebanon?
On this page
Short answer
You check the plot, hire a responsible engineer, file the application and collect the permit after technical approval and payment of all fees[1]. The application and plans must be signed by a responsible engineer and registered with the Order of Engineers in Beirut or Tripoli. The permit is issued by the head of the municipality, or the governor or caimacam outside municipal areas. The technical administration must decide within 2 months on an executed road, 6 months otherwise.
Also asked as: “What are the steps to get a building permit from a municipality in Lebanon?” · “How do I apply for a building permit in Lebanon?” · “Who issues building permits in Lebanon?” · “How long does a building permit take in Lebanon?”
This page follows the DGU consolidated text of Law 646/2004, and later amendments were not checked[1]. It covers what was published up to 17 October 2026, so confirm the current rules with the municipality's technical office or your engineer.
Key facts
- The law
- Law 646 of 2004 (Building Law), Art. 1[1]
- Who issues the permit
- the head of the municipality, or the governor or caimacam outside municipal areas[1]
- Institutions involved (2018 review)
- The Order of Engineers, General Directorate of Urban Planning and the municipality[2]
- Decision deadline
- 2 months on an executed road, 6 months otherwise[1]
- Land value estimate
- Certified copy due within one month of registering the application[1]
- Required in the file
- A soil-bearing study[1] and a car park on the plans
- Permit valid for
- six years, renewable once for two years[1]; a model-design permit two years, renewable once for two years[3]
- Fees
- No published schedule found; ask the municipality for a written figure
What needs a permit and who issues it
Law 646 of 2004 requires a permit before you build, convert, renovate or renew a building of any kind. The application and plans are signed by a responsible engineer and registered with the Order of Engineers in Beirut or Tripoli[1]. The permit is issued by the head of the municipality, or the governor or caimacam outside municipal areas, on technical approval. A 2018 academic review of the law names three institutions in the process: the Order of Engineers, General Directorate of Urban Planning and the municipality[2].
Not every job needs a full permit. Maintenance, retaining walls, plastering and renovation of lawful or regularised buildings need only a written declaration, signed by a responsible engineer, endorsed by the Order of Engineers and valid for one year[1].
Law 294/2022 offers a cheaper route for houses built to official model designs of at most 2 floors, 250 m² total, 150 m² per floor, 7.5 m high[3], with 50% off permit and municipal fees. It applies only in non-regulated areas and in regulated areas that allow housing. Governorate centres and main cities, archaeological and tourist areas, nature reserves, and landslide and flood zones are excluded, and unclassified areas marked agricultural in the master plan stay under the Higher Council of Urban Planning's rules. Each owner may use the regime once per owner. The law is in force for five years from 21 April 2022. By that count it ends around April 2027, and we could not confirm whether it has been extended, so ask the municipality or the DGU. More on small houses built from a model design.
The same academic review says that from 2014 the Interior Ministry issued four circulars, presented as easing permits, that let applicants skip notification to and checks by the Order of Engineers and the DGU. Its author questions whether they are legal[2]. The abstract also mentions 2017, and we could not confirm whether the circulars apply today. The Building Law text we read requires the engineer's registration with the Order[1].
Check the plot before you pay an engineer
A permit is only as good as the plot it is for. Start with an official Land Registry extract (ifadeh aqariyeh). It lists the owners, their shares, mortgages, seizures and pending court actions[4,5]. To request it you give the governorate, district, real estate zone and property number, plus section and block where they apply[4,6]. According to one law firm (Legalmondo, June 2025), the official certificate is issued only in person at the competent Land Registry office and costs USD 5[4].
A copy from OMT or online is unofficial. It is fine for a first look, but an official certificate is needed for a purchase or court use[4,5,6,7]. Ask the municipality whether the permit file needs the official one.
The register also records the land type. On mulk land you hold full ownership. On amiri land the State owns the land and you hold a right of use and disposal (tasarruf)[8]. Kallas Law Firm says a tasarruf holder may build on amiri land, but a permit is still needed.
Then check the zoning and the boundaries. A permit is granted under the laws and zoning rules in force on the day it is granted[9]. Kallas Law Firm advises reviewing the municipal master plan alongside the registry check. We found no source naming the office that gives a plot's zoning; the municipality and the DGU are the likely places to ask[8]. Here is how to find a plot's zoning and building ratios. Where the cadastral plan and the ground disagree, the plan prevails[10,11], so have the plot located on the plan before anything is drawn. See getting a cadastral map or survey.
Fees, deadlines and a silent municipality
The permit is issued only after technical approval and payment of all fees. The technical administration has 2 months to decide if the plot is on an executed road, and 6 months otherwise, for example when a planning project affects the plot or the Higher Council of Urban Planning must give its opinion. Other departments have 15 days, after which their approval is implicit[1].
Within one month of registering your application, the authority must give you a certified copy of the approved estimate of the plot's land value. If it refuses, you may pay the fees you believe are due, at your own responsibility, and the account is settled before the occupancy permit[1]. We found no fee schedule or rate per m². Ask the municipality and your engineer for a written estimate, and read how much a building permit costs.
Every new building must have a car park shown on the permit plans. You can build it or pay a replacement fee. That fee is recorded on the property's real folio and can be reclaimed if no car park is provided within 8 years[1]. Our sources do not give the amount of the fee.
If the deadline passes with no decision, you may apply to the competent authority within 6 months, directly or through a notary. You declare yourself implicitly licensed, attach the fees due and undertake to follow the permit file and the law[1]. No source we read covers the risks of relying on this later, for a sale or a registration, so ask a lawyer first. More in what to do if the municipality does not answer.
After the permit is issued
A permit is valid for six years, renewable once for two years[1]. Renewal is free if the permitted area does not grow. You must request it within 6 months of expiry, and the administration decides within one month. A renewal follows the rules in force at that time, except for rights already acquired by building the load-bearing parts. No slab or roof may be poured without a pouring permit signed by the responsible engineer. A model-design permit under Law 294/2022 is valid for two years, renewable once for two years[3].
If errors found later require the permit to be corrected, only what is already built counts as an acquired right. Unbuilt parts must be brought into line with the law[9]. If the facades are unfinished when the permit expires, you have one year to finish them. After that, a yearly fine of 15% of the permit fees is registered on the folio as a privileged debt[1]. When the building is finished, you apply for the occupancy permit.
How to get a building permit, step by step
- Get the official Land Registry extract. You, or someone acting for you, request it at the Land Registry office for the property's area[4,12]. Bring the governorate, district, real estate zone and property number, plus section and block where they apply[4,6]. Kallas Law Firm (October 2025) gives about 2 business days for a physical certificate, and times vary with office opening days[5]. Check that the owner named is you, or the seller you are dealing with, and note any shares held by other people.
- Ask the municipality about the plot. The permit comes from the municipality where the plot lies, or from the caimacam or governor outside municipal areas[1], so start there. Bring the extract and ask four things in writing: which zoning rules and building ratios apply to this plot number in this zone, whether a planning project or road plan affects it (that brings the 6-month deadline), the list of documents for the file, and the expected fees. We found no published document list, so get this answer on paper.
- Hire a responsible engineer. The engineer signs the application and plans, which are registered with the Order of Engineers in Beirut or Tripoli[1]. We could not confirm the Order's fees, so ask the engineer for a written quote that includes them.
- Order a soil-bearing study. It comes from a specialised soil-investigation office and must be attached to the application[1]. Its cost is not published, so get a written quote.
- File the application and ask for the land estimate. Ask the municipality which office takes the file, and keep a dated receipt. The authority owes you a certified copy of the land value estimate within one month of registering the application[1].
- Wait for technical approval, then pay the fees. The deadline is 2 months on an executed road, 6 months otherwise[1]. Pay only against official receipts and keep copies.
- Collect the permit and keep it with your papers. Check that it names your plot and the approved plans. Before each slab or roof is poured, the engineer signs a pouring permit[1].
It depends on
- Whether the plot is on an executed road. The decision deadline is 2 months on an executed road and 6 months otherwise[1]. Ask the municipality's technical office which applies to your plot.
- Inside or outside a municipal area. The permit is issued by the head of the municipality, or the governor or caimacam outside municipal areas[1]. Ask the municipality, or the caimacam's office, which body covers your plot.
- Whether work has already started. Work begun without a permit is stopped. If it conforms to the rules, the permit is granted with a fine of twice all the fees due[1] on the part already built, and if it does not conform it must be demolished. A violation goes on the real folio only at the request of the municipality or the technical administration, so a clean extract does not prove there is none. Violations built between 13 September 1971 and 31 December 2018 fall under Law 139/2019[14,15]. Ask the municipality, an engineer and a lawyer before you buy a plot with an unfinished structure.
Common questions
How long does a building permit take in Lebanon?
The law gives the technical administration 2 months on an executed road, 6 months otherwise[1] to decide, and other departments 15 days. Actual waiting times are not published, so ask the municipality when you file.
How long is a building permit valid?
What happens if the municipality does not decide in time?
You may apply to the competent authority, directly or through a notary, within 6 months after the deadline lapses. You declare yourself implicitly licensed and attach the fees due[1]. Ask a lawyer before relying on this.
Can I apply for a building permit from abroad?
The application and plans must be signed by a responsible engineer and registered with the Order of Engineers[1]. We found no rule on whether the owner must appear in person or whether an agent can file, so ask the municipality. If an agent can, the power of attorney is signed at a Lebanese embassy or consulate, or before a local notary, authenticated by the local authorities and then legalised by the Lebanese embassy or consulate[16,17,18,19].
Sources
Checked against these sources. The numbers in the text point here.
- 1.Law 646 of 16/12/2004 (Building Law), amending Legislative Decree 148 of 16/09/1983
Lebanese Republic, Ministry of Public Works and Transport, Directorate General of Urban Planning (DGU) · 16 Dec 2004 · read 17 Oct 2026
- 2.Building Permit: A Critical Review of the Legal Framework in Lebanon (abstract)
BAU Journal - Health and Wellbeing (Beirut Arab University, Digital Commons) · undated · read 17 Oct 2026
- 3.Law 294 of 14/4/2022: temporary reduction of fees for some building permits built to model designs
Lebanese University Legal Informatics Center (DGU copy of Law 294/2022) · 14 Apr 2022 · read 17 Oct 2026
- 4.How to Find Real Estate and Land Register Information in Lebanon
Legalmondo · 17 Jun 2025 · read 17 Oct 2026
- 5.Lebanon Asset Search: How to Find Real Estate and Company Ownership Records
Kallas Law Firm · 25 Oct 2025 · read 17 Oct 2026
- 6.OMT: Viewing Title Registers (Land Registry service page)
OMT (Online Money Transfer S.A.L.) · undated · read 17 Oct 2026
- 7.Viewing Title Registers Electively Through OMT
OMT (Online Money Transfer S.A.L.) · 13 Oct 2020 · read 17 Oct 2026
- 8.Definition of Real Property and Types of Ownership in Lebanese Law (Part One of the Practical Guide to the Code of Real Property)
Kallas Law Firm · 25 May 2026 · read 17 Oct 2026
- 9.Decree 15874 of 5/12/2005 implementing the Building Law, as amended by Decree 617 of 8/8/2007
General Directorate of Urban Planning (DGU), Ministry of Public Works and Transport · 5 Dec 2005 · read 17 Oct 2026
- 10.The Land Registry in Lebanese Law — Part Six of the Practical Guide to the Code of Real Property
Kallas Law Firm · 25 May 2026 · read 16 Oct 2026
- 11.Land Delimitation and Registration Works in Lebanese Law — Part Seven of the Practical Guide to the Code of Real Property
Kallas Law Firm · 25 May 2026 · read 17 Oct 2026
- 12.Inheritance in Lebanon: Probate, Estate Declaration and Inheritance Tax (2026)
Kallas Law Firm · 27 Jun 2022 · read 17 Oct 2026
- 13.Legislative and Administrative Land and Property Rights Framework. Lebanon
GLTN / UN-Habitat · May 2024 · read 16 Oct 2026
- 14.Law 139 of 9/7/2019 settling building violations committed 13/9/1971 to 31/12/2018
Lebanese University Legal Informatics Centre (copy of DGU text) · 9 Jul 2019 · read 17 Oct 2026
- 15.Law 139/2019 on settling building violations committed between 13/9/1971 and 31/12/2018 inclusive (Arts 3, 5, 7, 9 marked as amended by Law 10/2022)
Lebanese University Legal Information Center (legiliban) · 9 Jul 2019 · read 17 Oct 2026
- 16.Power of Attorney
Embassy of Lebanon, Washington DC · undated · read 17 Oct 2026
- 17.Legalization of Powers of Attorney not Drafted at the Consulate
Consulate General of Lebanon, New York · undated · read 17 Oct 2026
- 18.Power of Attorney
Embassy of Lebanon, The Hague · undated · read 17 Oct 2026
- 19.Services consulaires supplémentaires par courrier
Embassy of Lebanon, Brussels · undated · read 17 Oct 2026
Related questions
- How much does a building permit cost in Lebanon?We found no published price list: fees rest on a certified estimate of the plot's land value. Other costs, the model-design discount and how to get a quote.
- What does the Order of Engineers do in a building permit in Lebanon, and why do I need an engineer?No permit without an engineer: Law 646/2004 requires plans signed by an engineer and registered with the Order. What the Order does, step by step.
- How do I find the zoning and building ratios for a plot in Lebanon?No office is published for it: get the plot's extract, then have an engineer check the master plan and exploitation factors. Steps and what to ask.
- What if the municipality does not answer my building permit application?If no decision comes within 2 or 6 months, Law 646/2004 lets you declare yourself implicitly licensed. Deadlines, the filing, fees and the open risks.
- Is there a building permit fee discount for small model-design houses in Lebanon?Yes: Law 294/2022 halves permit and municipal fees for houses built to official model designs, up to 2 floors and 250 m². Who qualifies and the deadline.
- What should I check before buying land in Lebanon?Get an official Land Registry extract for the exact plot first, then check shares, land type, survey status, zoning and fees. Steps for buyers abroad.
- What is the occupancy permit in Lebanon and how do you get it?The permit to occupy a finished building, applied for by the owner with as-built plans. Steps, the one-month deadline, why flats need it, how to check it.
- Do I need a permit to renovate my apartment in Lebanon?It depends: renovating a lawful building needs an engineer's declaration, structural work a permit. Who signs, owners' consent, timing.